Central Link Light Rail Project

Seattle, Washington

"Let's stop talking and start digging!"


FOR DISCUSSION ONLY

Projected level of Federal support for Link

John Deeter, 6/24/01

Central Link is the most ambitious new-start urban rail project in the United States for the next 15 years. The full Phase I project -- Northgate to Sea-Tac -- is about 24 miles long, is estimated to cost about $4.2 billion (YOE), and is projected to generate 154,000 daily riders in 2020. The current estimate of available local funds for the Link project is $2.1 billion (YOE) -- almost exactly half of the expected total project cost -- and the current projected federal contribution is no more than $1.15 billion (see Board Workshop May/June 2001, Appendix I). This leaves a shortfall of nearly $1 billion if no other revenue source appears. I believe that Sound Transit should reasonably expect a considerably larger federal contribution than is currently projected -- large enough, if fact, to make the full Phase I (Northgate to Sea-Tac) achievable without any new infusion of local money.

There seems to be a general belief among many people close to the Link project -- almost folklore, if you will -- that there's a "hard" cap to the dollar amount of federal support Link can expect. But the actual numbers from FTA reports belie this belief: in fact, other large projects recently and currently in the funding pipeline have received very generous federal support. I will first discuss recent levels of federal support for rail projects, with special emphasis on four particularly large projects (Los Angeles Red line, the Hudson-Bergen LRT line, the proposed Orange County LRT line, and BART to SFO). I then review local assumptions about federal funding, starting with the ballot measures prepared for the 1995 vote (which failed) and the 1996 vote (which passed). Finally, I present a "strawman" proposal for phasing the Link project designed to leverage a high level of federal support.

Recent and Upcoming Rail Projects

I have extracted some relevant information about recent and upcoming rail projects in the United States from the recently released "USDOT Report on New Starts: Proposed Allocations for FY2002" (see Table A-1 in Appendix A attached below). The fractional federal share for most urban rail projects has generally been in the range 60 to 70 percent of total cost, and very rarely under 50 percent.

But the most telling comparision is with three other large projects: Los Angeles Red Line which was recently completed and for which no additional construction is currently planned; Hudson-Bergen LRT which was recently opened and construction of the second segment is just now getting started; BART to SFO, which is nearing completion and scheduled to open next year; and Orange County LRT which is still in preliminary engineering but currently stalled due to local uncertainties about the need and effectiveness of the project. Data for these four systems are presented in Table 1, which mainly contains information extracted from Table A-1.

--------------------------------------------------------------------
                          TABLE 1.
  Comparison of Seattle Link with other recent large rail projects
                     General Information
====================================================================
                   year 
                   first year         No,  Cap.   Fed.   Fed. rides
                   FFGA  comp-  lgth  of   cost   shr.   shr. per
                   sgnd  lete   (mi)  stn  (B$)   (B$)   (%)  day
--------------------------------------------------------------------
LA Red Line        1986  2000   17.4  16   $4.50  $2.35  52   120K*
   MOS-1           1986  1993   4.4   5    $1.44  $0.70  49   ...
Hudson-Bergen LRT# 1996  2005   15.7  23   $2.11  $1.10  52   66K
   MOS-1           1996  2000   9.6   16   $0.99  $0.60  61   31K
BART to SFO        1997  2002   8.2   4    $1.51  $0.75  50   74K
Orange Co. LRT     ...   ...    30.1  35   $3.74  $1.87  50   82K
Seattle Link       2001  ...    24    23   $4.20  $1.15  27   154K
   MOS-1 (propsd)@ 2002  2008   9.5   13   $2.05  $0.50  24   70K
--------------------------------------------------------------------
* Current ridership (early 2001), others are projected 2020 ridership.
# MOS-1 and MOS-2; a third MOS is planned that will bring the system
  length to 21 miles and ridership to 94K per day.
@ Capitol Hill to Henderson.  Estimated ridership with Royal Brougham 
  and Beacon Hill stations included, 60K without them.
--------------------------------------------------------------------

Table 2 shows a breakdown of funding sources for these projects -- federal new start funds; other (flexible) federal funds; state funds from every source other than purely local revenues; and funds from local revenues. The federal percentage share of the project total funds is also shown.

--------------------------------------------------------------------
                          TABLE 2.
  Comparison of Seattle Link with other recent large rail projects
                Funding sources and federal share  
====================================================================
                   Fed.    Other  Total
                   New     Fed.   Fed.    State  Local  TOTAL  Fed.
                   Starts  Funds  Funds   Funds  Funds  Funds  Shr.
                   (M$)    (M$)   (M$)    (M$)   (M$)   (M$)   (%)
--------------------------------------------------------------------
LA Red Line
   MOS-1           $605    $91     $696   $0     $743   $1439   48
   MOS-2           $667    $52     $719   $0     $1020  $1739   41
   MOS-3           $681    $246    $927   $0     $384   $1311   71
   Total           $1953   $389    $2342  $0     $2147  $4489   52
Hudson-Bergen LRT 
   MOS-1           $604    $282    $886   $106   $0     $992    89
   MOS-2           $500    $154    $654   $562   $0     $1215   54
   Total           $1104   $436    $1540  $668   $0     $2207   70
BART to SFO        $750    $0      $750   $152   $608*  $1510   50
Orange Co. LRT     ...     ...     $1870  ...    $1871  $3741   50   
Seattle Link       
   MOS-1 original  $500    $0      $500   $0     $1750  $2250   22
   MOS-1 proposed@ $500    $0      $500   $0     $1550  $2050   24
   Phase I#        $1150   $0      $1150  $0     $2100  $4200   27
--------------------------------------------------------------------
NOTE:  Reported in $YOE.  Totals may not add due to rounding.
* Includes $113 M in SFO funds and $27 in CAPRA funds beyond the
  federal project.
@ Capitol Hill to Henderson (9.5 miles).
# Northgate to Sea-Tac (24 miles).  Federal new starts estimate is
  the sum of $500 M from TEA-21 plus an estimated $650 M maximum from
  the next two funding cycles (2004-2015).  Without additional funds 
  the project shortfall would be $950 M.
--------------------------------------------------------------------

Some comments on the four systems (besides Link) shown in Tables 1 and 2:

The Los Angeles Red Line got $2.34 B federal support (mainly new start money) out of a $4.5 B project -- and was in line for more federal money until LA decided not to build any more subways. It is currently carrying about 120,000 daily riders, a year after opening the third and final segment. If the Red line were started today -- some 15 years later -- its total cost should be inflated by about 80 percent (i.e., multiplied by a factor of 1.8), and would therefore be about $8 billion. (This assumes a construction mid-year of 2008, compared to the actual mid-year 1993.)

Hudson-Bergen LRT (Jersey City and northward, on the west side of the Hudson river, opposite Manhatten) is the largest new project currently under construction. MOS-1 opened last year, and the FFGA for MOS-2 was recently signed. MOS-1 got a whopping 89 percent in federal funds -- 61 percent from new starts and 28 percent from flexible funds -- and the state put up the rest! MOS-2 isn't doing as well -- only 54 percent federal support. These two segments total $2.2 B -- and there's a third segment that hasn't reached the FTA yet, so the total project will be well over $3 B.

Orange County's light rail project has been run past the FTA -- the total cost is $3.74 B and they expect 50 percent federal support. Right now this project is on indefinite hold because of local questions about its effectiveness.

Finally, BART to SFO -- a very controversial project now priced at over $1.5 B -- is getting 50 percent federal support. The federal share was orginally about 60 percent, but cost overruns after the FFGA was signed have diluted it.

How does Link compared to the three new projects (LA Red line, Hudson-Bergen LRT, and Orange County LRT)? Link Phase I projected ridership in 2020 (154 thousand per day) is comparable to the Red Line ten years after completion, and much larger than the projected ridership for either of the other two systems. On the other hand, Link is much less expensive than the Red Line (after adjusting for inflation), and comparable in cost to the other two. Thus Link will be significantly more cost-effective than any other recently started, large urban rail system in the country.

What sort of federal support should we expected for the Link project? The signed FFGAs for the three segments of the Red line specified 59 percent federal support, but this was diluted to 52 percent due to significant cost increases during construction. Hudson-Bergen LRT is getting 70 percent and Orange County LRT expects 50 percent, and none of these "large" systems is as cost-effective as Link is expected to be. And other recent projects have received federal shares of 60 or even 70 percent, although the cost of any one of these projects has generally been well under $1 billion (see Table A-1 in Appendix A).

Thus, it is not fair to argue that because no other project is currently slated to receive over $500 million for a single MOS, the Link project is likewise subject to a similar limit. In fact, the premise isn't even true -- LA Red Line, Hudson-Bergen LRT, and Portland's Westside Line have all gotten over $500 M for a single FFGA. The examples of the LA Red line and Hudson-Bergen also demonstate that a large project with a projected large ridership is fully eligible for a federal contribution well in excess of 50 percent, with multiple MOS's and large annual grants continued over as long a period as 15 years.

A federal share of 50 percent of the $4.2 billion total estimated cost of the Link project provides $2.1 billion, and (fortuitously!) the available local match provides almost exactly the other $2.1 billion. The bottom line is that the full Phase I (Northgate to Sea-Tac) is financially feasible if the region gets all the federal funding it is entitled to.

On the other hand, Link's consultant projects that Link should expect no more that 4 percent of federal "new-start" money over the 2006-2015 time interval, or some $650 million. (See Appendix I in the "Central Link Board Workbook, May/June 2001".) Together with the $500 million already committed from TEA-21, this amounts to just $1.16 billion, and leaves the project nearly $1 billion short of what is needed for completing. But Link is the "premier" federal project for the next 15 years -- like the Red line was for the previous fifteen. Aggressive lobbying by the region should easily raise the Link share of the pot to something closer to 10 percent (instead of the 4 percent suggested by the consultant), which would allow Link to reach Northgate before 2015.

History of RTA/Sound Transit assumptions about Federal support

How did local assumptions regarding the target level of federal support for light rail in the Puget Sound region evolve, from the one developed in 1994 and rejected by the electorate in 1995 to the LPA (and MOS-1) adopted locally in 1999 and accepted by the FTA and Congress in 2000? [Note: The FFGA for this latter plan was signed in January 2001, but the new Secretary of Transportation, Mr. Mineta, has annulled this agreement. Sound Transit is currently preparing a revised MOS-1 and possibly a new LPA as well.]

The evolution of targeted federal support, as deduced from published plans, is summarized in Table 3. It should be noted that the level of federal support is generally targeted at around 30 percent, and in a couple of instances a good deal lower. Only two times has a target of 50 percent or greater been mentioned: (1) in 1999 a level of 50 percent was used in negotiations with the FTA around the time the current LPA was adopted and the total cost for Phase I was still a fairly low $2.9 B; and (2) in late 2000 a level of 69 percent was assumed for MOS-2 in order to build the segment from Lander St. to Sea-Tac without relying on any further North King Co. funds (they were exhausted in MOS-1 to get to 45th St.).

--------------------------------------------------------------------
                            TABLE 3.
     Previous assumptions about Federal and State support 
        for the Central Puget Sound Light Rail Project  
====================================================================
                           Fed.   State  Local  TOTAL  Fed. Fed/
                           Funds  Funds  Funds  Funds  Shr. yr@
                      yrs  (M$)   (M$)   (M$)   (M$)   (%)  (M$) Ref.
--------------------------------------------------------------------
RTA Plan, Oct. 1994*  16   $948   $803   $2264  $4015  24   100  (a)
Sound Move, May 1996* 10   $547   ...    $1149  $1696  32   92   (b)
Sound Transit, 1999@  10   $1450  ...    $1450  $2900  50   145  (c)
Link MOS-1, 2000@     10   $500   ...    $1000  $1500  33   50   (d)
Link Phase I, 2001@
   MOS-1              13   $500   ...    $1750  $2250  22   ...  (e)
   MOS-2              13   $930   ...    $420   $1350  69   ...  (e)
   Total              13   $1430  ...    $2170  $3600  40   110  (e)
Link Phase I@         12   $1150  ...    $2200  $3600  32   96   (f)
--------------------------------------------------------------------
* 1995 dollars.   @ YOE dollars.

(a) RTA Master Plan (10/29/94).  Assumes 43.6 percent federal plus 
    state support for all rail ($2.0B/$4.6B, from Table 2, p. 64), 
    and 20 percent state support (pp. 39, 67).

(b) Sound Move (5/31/96).  Assumes 30 percent federal contribution 
    for South King Co. subarea.

(c) New Starts FY2000, USDOT (1999).  Phase I, Northgate (?) to 
    Sea-Tac.

(d) New Starts FY2002, USDOT (2001).  Original FFGA for University
    District to Lander St.

(e) Sound Transit (Jan. 2001).  Amended FFGA.

(f) Board Workbook (May/June 2001).  45th St. to Sea-Tac.  Note that
    there is a $250 M shortfall.
-------------------------------------------------------------------

Although the percentage federal contribution has fluctuated widely, the annual dollar value has been fairly stable -- around $100 M (YOE dollars). In order to compare the first two entries (both given in 1995 dollars) with the remaining ones (YOE dollars), I multiplied the former by 1.68 to account for inflation to 2008 (approximate mid-year for the last two entries). The lowest value ($50 M per year) is clearly an anomaly, and is due to the small federal contribution from TEA-21. On the other hand, the highest value ($145 M per year) may actually be an achievable target, provided Sound Transit is able to present a more convincing case that it needs and deserves this level of federal support.

Does the principle of "subregional equity" affect in any way how much federal support will be requested and how it will be distributed among the five subregions?

The "Master Plan" adopted by the RTA Board on October 29, 1994, contained a very clear statement on this matter:

This plan failed to win approval at an election in spring 1995. A second plan, developed in late 1995 and early 1996, hedged on this clear language. The "Ten-year Regional Transit Plan", adopted on May 31, 1996, and approved the voters in November 1996, contains these somewhat ambiguous statements in Appendix B, "Financial Policies": The practical meaning of "an assumption for federal funding" may be deduced from Appendix A, "Detailed description of facilities and costs", where North King subarea (Seattle and Shoreline) is allocated $452 million from federal grants against capital costs of $1,381 million for light rail (33 percent), while South King is allocated $163 million in federal funds against capital costs of $543 million for light rail and commuter rail combined (30 percent). This indicates a strong tendancy towards distributing federal support as evenly as possible, even in the face of expensive tunnelling in north Seattle for the segment out to the University that clearly forms the core of the entire light rail system and generates a substantial fraction of the ridership as well. It therefore seems that "subregional equity" was tacitly recognized in the 1996 plan as perhaps a secondary goal in the distribution of federal support.

Strawman proposal for Link phasing

ST has to be much more aggressive in seeking federal funds. Central Link stands out as the number one project among those now coming into the federal funding pipeline -- high ridership serving dense urban areas. Other, lower rated projects have been getting 60-70 percent federal funding. Total cost for Northgate to Sea-Tac is $4.2 B, and $2.25 B in local funds is available ($1.75 B from North King, $500 M from South King). $1.4 B federal share (39 percent of $3.6 B) gets us to 45th St., and $2.0 B (48 percent of $4.2 B) gets us to Northgate. People should stop being timid about asking for our fair share of the federal pot.

It is essential that a plan be developed for continuing the Link project to completion beyond MOS-1 -- there may very well be 2 or 3 further MOS's down the road.

The proposal outlined here is deliberately aggressive in the sense that it seeks to maximize the federal contribution to the project. Thus MOS-1 is reduced to the absolute minimum (Capitol Hill to Lander) that will retain the $500 M federal contribution from TEA-21. At the beginning of the next funding cycle (FY2004) Sound Transit then presents the federal authorities (FTA and Congress) with a very large ridership MOS-2 -- going both south (Lander to Henderson) and north (Capitol Hill to 45th) -- and requests at least a 50 percent federal contribution for these two segments. (See Table 4.)

---------------------------------------------------------------------
                                TABLE 4. 
               Strawman phasing plan for Link Phase I
=====================================================================
                                                                 Fed.
                               Opens  Cost     Local    Fed.     Pct.
---------------------------------------------------------------------
MOS-1   Capitol Hill to Lander 2008   $1350 M  $850 M   $500 M   37   
MOS-2A  Lander to Henderson    2008   $700     $300     $400     57
MOS-2B  45th to Cap. Hill      2012   $900     $400     $500     56
MOS-3A  Henderson to Sea-Tac   2012   $700     $500     $200     29
MOS-3B  Northgate to 45th      2014   $600     $250     $350     58
---------------------------------------------------------------------
Totals                                $4250 M  $2300 M  $1950 M  46
---------------------------------------------------------------------

Note that the segment Capitol Hill to Henderson specified in Scenario 4 as the "MOS" is here broken into two parts, MOS-1 (Capitol Hill to Lander) and MOS-2A (Lander to Henderson). This allows local funds for the Rainier Valley segment to be used to leverage a federal match, assumed here (and in much of the table) at a reasonable 57 percent. (Note that the entire segment from Capitol Hill to Henderson is projected to open in 2008 as the "initial operating system". This initial system (MOS-1 plus MOS-2A) recieves overall a modest 44 percent federal share while being very competative in terms of cost per rider, etc., compared to other systems currently in the pipeline.) The strategy is to hold off MOS-2A until the beginning of the next federal funding cycle (FY2004), and pool it with MOS-2B (Capitol Hill to 45th) after the SEIS for the Montlake alignment is completed. The combined MOS-2 is actually not much larger than MOS-1 -- $1.6 B compared to $1.35 B -- but it generates a whopping additional ridership of 70K/day. The low cost per rider fully justifies something close to the federal maximum of 80 percent, but I've written down a modest 56 percent, or $900 M. And it wouldn't be unreasonable to start negotiations at $1 B (62 percent).

Once the initial operating system is opened in 2008, Sound Transit will be in a good position to ask for federal support for MOS-3, which will push Link to Northgate in the north and Sea-Tac in the south before 2015. In this way it may be possible to build the complete Phase 1 (Northgate to Sea-Tac) without any additional local money beyond the $2.1 B already in hand -- assuming modest cost-saving measures (such as the Montlake alignment instead of Portage Bay) and modest contributions from other sources (such as a sales-tax rebate from the State).

References


\

APPENDIX A.

USDOT Annual Report on New Starts Proposed Allocations FY 2002

Extracted from FTA's "Annual Report on New Starts: Proposed Allocation of Funds for Fiscal Year 2002". See <http://www.fta.dot.gov/library/policy/ns/ns2001/ns2002.html>

----------------------------------------------------------------------
                        Table A-1.
USDOT Annual Report on New Starts Proposed Allocations FY 2002
                    General Information
======================================================================
                         year  year        No. Cap.   Fed.  Fed. rides
                   Sta-  FFGA  to    lngth of  cost   shr.  shr. per
                   tus   sgnd  open  (mi)  stn (M$)   (M$)  (%)  day
----------------------------------------------------------------------
Atlanta/N Springs  Open  1994  2000  1.9   2   $463   $371   80  33K
Boston Transitway  UC    1994  2003  1.0   3   $601   $331   55  22K
Chicago/Douglas    UC*   2001  2005  6.6   11  $451   $320   71  27K
Dallas/No-Central  UC    1999  2003? 12.5  9   $517   $333   64  17K
Denver/SE LRT      UC    2000  2008  19    14  $882   $525   60  38K
Denver/Southwest   Open  1996  2000  8.7       $176   $120   70  22K
Tri-Rail Commuter  UC    2000  2005            $327   $110   34  42K
Houston Bus Plan   UC    1994  2004            $625   $500   80
Los Angeles 
  Red MOS-3        Orig  1993  n/a   12.3  9   $3044  $1416  47
  Red MOS-3A       Open  1993  2000  6.3   3   $1311  $681   52  120K
  LRT MOS-3B       Stdy              6                           15K
Maryland/MARC      Open  1995  2001            $132   $105   80
Memphis/Medical    UC    2000  2004  2.5   6   $75    $60    80  4200
Minn-StP/Hiawatha  UC    2001  2004  11.5  15  $549   $274   50  25K
Hudson-Bergen (1)  Open  1996  2000  9.6   16  $992   $604   61  31K
Hudson-Bergen (2)  UC    2000  2005  6.1   7   $1215  $500   41  35K
Newark Rail (1)    UC*   2000        1     5   $208   $142   68  13K
Pittsburgh Recnstr UC    2001  2004            $384   $100   26  24K
Portland/Westside  Open  1992  1998  17.7  20  $964   $630   65
Portland/Interst   UC    1990        5.6   10  $350   $257   73  18K
Sacramento/South   UC    1997  2003  6.3       $222   $111   50  25K
Salt Lake No-So    Open  1995  1999  15        $312   $237   76  26K
Salt Lake Univ.    UC    2000  2002  2.5   4   $106   $85    80  7600
SF BART to SFO     UC    1997  2002  8.2   4   $1510  $750   50  74K
St Louis/St Clair  UC    1996  2001  17.4  8   $339   $244   72
San Diego/Mssn E   UC*   2000  2005  5.9   4   $431   $330   77  11K
San Jose/Tasman W  Open  1996  1999  7.6       $325   $183   56  7500
San Juan/Tren Urb  UC    1996        10.7  16  $1653  $708   43  113K
Washington/Largo   UC    2000  2004  3.1   2   $434   $260   60  28K
----------------------------------------------------------------------
Baltimore/Dbl-Trk  Pend                        $154   $120   78  44K
Chicago/SW Comm.   Pend*                       $165   $128   78  14K
Seattle Link (1)   Revw* 2001        7.2   10  $1500  $500   33  87K
---------------------------------------------------------------------
Chicago/NCC Comm.  Dsgn                        $236   $145   61  8400
Dallas/Trinity II  Dsgn              25    5   $184   $46    25  11K
Little Rock/River  Dsgn              2.1   9   $13.2  $8.6   65  1000
LOSSAN Improv.     Dsgn                        $36    $24    67
Miami/Busway       Dsgn              11.5  12  $89    $23    26  8800
New Orleans/Canal  Dsgn              5.5   37  $157   $125   80  31K
No. San Diego      Dsgn*             23.7  15  $332   $152   46  15K
San Franciso/3rd   Dsgn              5.4   19  $531   $0     0   71K
Seattle Link (2,3) Dsgn@             16.3  13  $1350  $931   69  70K
----------------------------------------------------------------------
Austin LRT         PE#               14.6  16  $739   $369   50  37K
Charlotte/So LRT   PE                11    19  $331   $167   50  15K
Cincinnati/IS LRT  PE#               19    24  $875   $431   49  24K
Cleveland/BRT      PE                9.8       $229   $135   59  29K
Hartford/BRT       PE                9.6   12  $82    $52    63  8800
Houston/Astro LRT  PE                7.5   17  $300   $0     0   33K
Las Vegas/ext.     PE                4.7   11  $597   $210   35  63K
Los Angeles
  Eastside LRT     PE                5.9   8   $750   $402   54  15K
  Valley E-W BRT   PE                14.2  13  $300   $0     0   24K
Miami/N 27th BRT   PE#               9.5   10  $88    $61    69  10K
New Orleans/Desire PE                2.9   22  $93    $65    70  15K
New York/LIRR Acc. PE                4     2   $4344  $2172  50  351K
Orange Co./Center  PE                30.1  35  $3741  $1871  50  82K
Phoenix/E Valley   PE@               20.3  28  $1076  $533   50  24K
Raleigh/Regional   PE                34.7  16  $755   $377   50  18K
San Diego/Mid ext  PE*               3.4   3   $117   $42    36  12K
San Juan/Minillas  PE                1     2   $477   $383   80  14K
----------------------------------------------------------------------
* "Highly recommended", 
# "Not recommended"
@ Not rated
others "recommended" 
----------------------------------------------------------------------

John Deeter 6/24/01


stamp
Send e-mail to: John Deeter bj556@scn.org

This is a link to John Deeter's home page.


SCN Home Page
Seattle Community Network
SCN Member Pages